Lineset size, extra charge per foot, and a sizing chart. Also in the Blueprint iOS app.
Turn these numbers into a build plan.
| Tons | Liquid | Suction, to 50 ft | Suction, long line |
|---|---|---|---|
| 1.5 | 1/4 in | 5/8 in | 3/4 in |
| 2 | 3/8 in | 3/4 in | 3/4 in |
| 2.5 | 3/8 in | 3/4 in | 7/8 in |
| 3 | 3/8 in | 3/4 in | 7/8 in |
| 3.5 | 3/8 in | 7/8 in | 7/8 in |
| 4 | 3/8 in | 7/8 in | 1 1/8 in |
| 5 | 3/8 in | 1 1/8 in | 1 1/8 in |
Save this lineset spec and install checklist below: the parts list, the steps through the vacuum, and the charge step marked for a pro with EPA 608 certification.
Finished the refrigerant line sizing? Snap a before and after. The photo maker lines them up into one image you can post, and a free Blueprint account keeps the photos with your measurements and materials.
A 2.5 ton split system with 25 ft of line (33 ft equivalent) takes a 3/8 in liquid and 3/4 in suction line and about 6.0 oz of extra R-410A.
Mount the units
Set the outdoor unit level on a pad or brackets and mount the indoor unit or air handler, keeping the run as short and straight as you can.
Run the line set
Route 25 ft of 3/8 x 3/4 in line with no more than 4 sharp bends, insulation intact, and the drain line sloped down.
Make the connections
Cut square, deburr, flare or braze per the unit manual (braze under nitrogen flow), and torque flare nuts to spec.
5 steps ยท 5 tools ยท 4 materials
2 more steps, the full tool list and a shopping list you can check off as you go.

Your plan is 60% built. Save it.
3/5Run a 3/8 x 3/4 in R-410A line set, 25 ft
Finished in 1 to 2 days, plus a pro visit to charge ยท $490 DIY
Built for your liquid of 3/8 in. Your first plan saves free. No card needed.
Or save it with just your email
We send a link; open it and this plan is your first project. Your first plan saves free. No card needed.
| Tons | 25 ft | 50 ft | 75 ft | 100 ft | 150 ft |
|---|---|---|---|---|---|
| 1.5 | 1/4 x 5/8 | 1/4 x 5/8 | 1/4 x 3/4 | 5/16 x 3/4 | 5/16 x 3/4 |
| 2 | 3/8 x 3/4 | 3/8 x 3/4 | 3/8 x 3/4 | 3/8 x 3/4 | 3/8 x 3/4 |
| 2.5 | 3/8 x 3/4 | 3/8 x 3/4 | 3/8 x 7/8 | 3/8 x 7/8 | 3/8 x 7/8 |
| 3 | 3/8 x 3/4 | 3/8 x 3/4 | 3/8 x 7/8 | 3/8 x 7/8 | 3/8 x 7/8 |
| 3.5 | 3/8 x 7/8 | 3/8 x 7/8 | 3/8 x 7/8 | 3/8 x 7/8 | 3/8 x 7/8 |
| 4 | 3/8 x 7/8 | 3/8 x 7/8 | 3/8 x 1 1/8 | 3/8 x 1 1/8 | 3/8 x 1 1/8 |
| 5 | 3/8 x 1 1/8 | 3/8 x 1 1/8 | 3/8 x 1 1/8 | 3/8 x 1 1/8 | 3/8 x 1 1/8 |
| Tons | 25 ft | 50 ft | 75 ft |
|---|---|---|---|
| 1.5 | 1/4 x 3/4 | 1/4 x 3/4 | 1/4 x 3/4 |
| 2 | 3/8 x 3/4 | 3/8 x 3/4 | 3/8 x 7/8 |
| 2.5 | 3/8 x 7/8 | 3/8 x 7/8 | 3/8 x 7/8 |
| 3 | 3/8 x 7/8 | 3/8 x 7/8 | 3/8 x 1 1/8 |
| 3.5 | 3/8 x 1 1/8 | 3/8 x 1 1/8 | 3/8 x 1 1/8 |
| 4 | 3/8 x 1 1/8 | 3/8 x 1 1/8 | 3/8 x 1 1/8 |
| 5 | 1/2 x 1 1/8 | 1/2 x 1 1/8 | 1/2 x 1 3/8 |
Lines over 150 ft are outside most residential limits. The outdoor unit's installation manual always wins over a general chart.
| Liquid line OD | R-410A | R-454B | R-32 | R-22 (legacy) |
|---|---|---|---|---|
| 1/4 in | 0.25 oz | 0.24 oz | 0.23 oz | 0.28 oz |
| 5/16 in | 0.40 oz | 0.39 oz | 0.36 oz | 0.45 oz |
| 3/8 in | 0.60 oz | 0.58 oz | 0.54 oz | 0.67 oz |
| 1/2 in | 1.20 oz | 1.16 oz | 1.08 oz | 1.34 oz |
Extra charge = (line length - precharge length) x oz per foot. Most split systems are precharged for 15 ft and mini-splits for 25 ft (check the nameplate). Suction vapor weighs so little it is ignored.
Result: 3/8 in liquid, 7/8 in suction (3/4 in acceptable), 1.13 lb (18.0 oz) extra charge.
The suction line carries cold vapor and the compressor oil back to the outdoor unit. Too small and the pressure drop costs capacity; too big and the vapor moves too slowly to carry oil up a vertical riser. That is why long horizontal runs step up a size, but a riser (outdoor unit above the indoor unit) stays at the standard size and gets an oil trap at the bottom and every 20 ft or so of lift.
| Indoor unit | Liquid | Suction |
|---|---|---|
| 12,000 BTU | 1/4 in | 3/8 in |
| 18,000 BTU | 1/4 in | 1/2 in |
| 24,000 BTU | 1/4 in | 5/8 in |
| 36,000 BTU | 3/8 in | 5/8 in |
Mounting units, running and insulating the line set, flaring, the nitrogen pressure test and pulling a vacuum are within a careful DIYer's reach, and pre-charged DIY mini-splits are sold for that. Opening a system, recovering old refrigerant and adding charge require EPA Section 608 certification. R-32 and R-454B are A2L (mildly flammable) refrigerants: follow the unit manual for brazing, leak detection and charging. The next steps for the install are the condenser circuit in the electrical load calculator, duct runs in the ductwork sizing calculator, filters in the MERV filter guide and payback in the energy savings calculator.
Chart explaining MERV scale and correlating ratings to air quality function
Max length calculator (35 ft minus elbows), 8 install steps, wall vs roof vs soffit, approved duct, clearances, cleaning and FAQ
Wire gauges, circuit breaker sizes, electrical codes, and safety guidelines